  1. No work at all since the demo of the existing...

    No work at all since the demo of the existing building several months ago.
  2. 2 different projects-2 different...

    2 different projects-2 different suppliers-Quadrozzi for the Freedom Tower, Greco for the Memorial
  3. Thread: Fulton Center

    by mkeit
    Replies
    1,433
    Views
    601,128

    Foundation work is well under way. Secant piles...

    Foundation work is well under way. Secant piles along the east wall and jet grouting around the Corbin Building.
  4. The Wendys has been closed since construction...

    The Wendys has been closed since construction began. The west wall of this building was rebuilt. They are still doing work on the area just east of 1 Mad Pk and west of Wendys--a basement level with...
  5. Thread: NYC Hotel News

    by mkeit
    Replies
    1,134
    Views
    611,155

    The 28/6th Ave Starwood site was a failed...

    The 28/6th Ave Starwood site was a failed apartment project called REMY. The completed foundation was backfilled over a year ago.
  6. Replies
    14,512
    Views
    6,938,075

    Zensteeldude; when you refer to 'erecting...

    Zensteeldude;

    when you refer to 'erecting steel', do you mean falsework?
  7. As of today-no work on the site beyond removing...

    As of today-no work on the site beyond removing some of the debris from the demolition.
  8. Replies
    1,095
    Views
    404,587

    Update-3/22- the bases for the arches are...

    Update-3/22- the bases for the arches are installed at street-level; the concrete for the building floor has been poured.

    Crews are working 7 days/week. There will be no service at the station...
  9. Replies
    1,095
    Views
    404,587

    96th St

    When I was there 2 weeks ago, the steelwork to support the new house was at ground level on the east side.
  10. Replies
    64
    Views
    38,378

    NY Construction News named Yves one of its Top...

    NY Construction News named Yves one of its Top Projects of 2008. It says it was completed in Feb 08-yet it does not seem occupied. Is there an entrance?

    Also-the 7th Ave sidewalk is 6" higher...
  11. The drill is from Warren George- a test drilling...

    The drill is from Warren George- a test drilling company.
  12. This may be revived-there is test drilling at...

    This may be revived-there is test drilling at the site this week.
  13. Replies
    14,512
    Views
    6,938,075

    One of the tower cranes has been raised. They...

    One of the tower cranes has been raised. They are using a patented support -the pqatent # is on a sign on the structure. It is different from the usual lifting device. The inventor-Larry Davis-is...
  14. Replies
    2,360
    Views
    1,015,372

    Yonkers' previous crane had a 200 Ton...

    Yonkers' previous crane had a 200 Ton capacity-this one is 240 Tons.
  15. Replies
    11
    Views
    8,961

    Maybe it is easier and faster then sweeping. ...

    Maybe it is easier and faster then sweeping. Some buildlings in the 20's between 6th and Bway-where I walk in the mornings-use soapy water and then rinse.
  16. Replies
    67
    Views
    31,262

    Keep in mind that this company had nothing to do...

    Keep in mind that this company had nothing to do with either of the fatal collapses.
  17. They say 'columns', not temporary.

    They say 'columns', not temporary.
  18. Replies
    744
    Views
    222,850

    The 2 TBMs will go in at 26 st. They should...

    The 2 TBMs will go in at 26 st. They should arrive in a few months. There will be several large pieces and it will take time to install them.

    Since the rock dips between 26 and 29th streets, a...
  19. Poll: I guess the strengthening work on the 40th St...

    I guess the strengthening work on the 40th St side will be for nothing.
  20. Replies
    185
    Views
    124,970

    While progress has been made on the tunnels to...

    While progress has been made on the tunnels to Manhattan. the work in Queens has not moved far. For the last 8 months, the two shafts excavated in Sunnyside Yards have been flooded. A sub...
  21. Replies
    3,812
    Views
    1,620,224

    You can see the arches from the Vesey St...

    You can see the arches from the Vesey St Bridge-but at a bad angle.
  22. Replies
    744
    Views
    222,850

    Plus it is too deep. Cut and cover is not...

    Plus it is too deep. Cut and cover is not practical below 30', especially in rock. This project is 80' deep in order to pass under the PRR and Lincoln tunnels.
  23. Replies
    95
    Views
    57,698

    Foundation work has been under way for the last...

    Foundation work has been under way for the last month. It was delayed because the ground was contaminated ( and probably still is).
  24. Replies
    744
    Views
    222,850

    # 7 extension

    The construction work is really making progress. Shaft construction is underway at both the 26th St and 34th St sites. A storage location is set up at 41/10 (SW corner), but a new building project...
  25. Replies
    1,095
    Views
    404,587

    And the E is the worst because of the constant...

    And the E is the worst because of the constant presence of homeless. This morning, 7:15 at Union Tpke, the conductors car had 3.