Thread: Fulton Center

  1. #841
    Forum Veteran MidtownGuy's Avatar
    Join Date
    Mar 2005
    Location
    East Midtown
    Posts
    6,832

    Default

    It's wonderful news about the Corbin building. I love the way the escalator will carry folks past the exquisite old brickwork.

    The Corbin Building abuts the site for the future glass-domed Fulton St. station, and was once scheduled for demolition, but preservation groups banded together in 2003 and got the M.T.A. to preserve the building instead.
    It ought to be common sense. Just look at that thing.

  2. #842

    Default

    The MTA has requested bids for the Fulton Street Transit Center Enclosure.
    Bids are due on 4/15.

    http://mta.info/nyct/procure/contracts/A-36125sol.pdf

  3. #843

    Default Today..

    Circular opening for the OculusClick image for larger version. 

Name:	DSC_0033.jpg 
Views:	348 
Size:	82.0 KB 
ID:	9259

  4. #844

    Default

    You truly feel like your in a third-world country walking through this station.

  5. #845

    Default

    Only three or four more years!

  6. #846
    Random Personality
    Join Date
    Aug 2005
    Location
    Woodside, Queens
    Posts
    950

    Default

    I really can't wait for this thing to be done [crosses fingers]. This connector should really help in making what is sometimes a very frustrating transfer point much easier to use.

  7. #847

    Default

    April 23, 2010
    3 Questions for Uday Durg, Fulton Transit Center


    Uday Durg has been working to build the Transit Center since 2002
    Unlike other major mass-transit projects like World Trade Center Transportation Hub or South Ferry Terminal, construction of the Fulton Street Transit Center occurs around four active subway platforms while nine train lines run 24 hours a day.

    But for the Metropolitan Transportation Authority (MTA) capital construction team, managing heavy ridership during major construction projects is inherent in the building process. Already the Transit Center team has deconstructed one-quarter of a city block, excavated 50 feet below the street, underpinned a landmarked building, and demolished approximately a half-miles worth of interior ramps -- all while millions of weekly subway riders swarm the station.

    Uday Durg, P.E., is the MTA's program executive for Lower Manhattan projects. A highly trained engineer with more than 20 years experience at the MTA, Mr. Durg oversees all design and construction of the $1.4 billion Transit Center. He wrapped up the same work on the new $530 million South Ferry Terminal last spring, a mega project that was completed in less than five years, even though a 400-year-old Battery fort wall was discovered in the middle of mass excavation.

    At the Transit Center, Mr. Durg has seen designs evolve as budgets changed and the construction market constricted. In 2008, MTA Capital Construction, led by President Michael Horodniceanu, divided the Transit Centers many construction components into separate contracts -- a plan that has helped keep costs down, balance labor needs, and maintain constant building.

    Familiar and esteemed among the Lower Manhattan community, Mr. Durg and his team are proving that massive construction work in one of New Yorks single busiest areas can be a source of optimism, rather than an interference. We asked Mr. Durg three questions about how he manages the complexities of Transit Center construction, and what he enjoys most about it.

    Whats it like running a project that has multiple contracts that are being executed simultaneously?

    Mr. Durg: The biggest challenge is coordinating all of the active work on the various contracts. Theres so much to focus on in terms of delivery of materials and in terms of labor on the job site -- and it all has to be coordinated. Getting materials in and out of Lower Manhattan can be very difficult and because this is closely tied to productivity, it has to be carefully planned so that the materials arrive when we need them to.

    Ive also got to worry about all the people that flow through this area on a daily basis. The job is right on Broadway and over 300,000 riders come through this complex every day. We are doing all this heavy, civil engineering and construction while maintaining service on the 4/5 -- one of the most crowded lines in the system -- plus the A/C line. In addition, we sometimes have more than 100 workers here a day, plus a lot of weekend work -- all the work on the A/C platform is on the weekends. So clearly, the safety of the public and our workers is one of our top priorities.

    Right now I have three contractors working simultaneously: Judlau, Skanska, and WDF. Theyre each performing a lot of work at the same time, which means we have a significant amount of material that has to be brought in and hauled out. But in the job site, there havent been conflicts yet in terms of the space. It has a lot to do with the way the packages were put together. They need each other to complete their contracts, and theyre all in the same business and respect each other.

    Another major challenge is already completed: The critical underpinning of the Corbin Building is done. That is one of the significant achievements in the last couple of months, because its a historic building, built in 1879, and we proceeded with this work deliberately and carefully to minimize any settlement. But now weve passed that critical stage. The building is underpinned.

    How have the changes inside the station affected riders?

    We have closed all the ramps on the east and west sides of the A/C platform, and all the ramps have now been deconstructed. Weve put temporary stairs in at both ends of the platform, and although it took a few weeks for riders to adjust, the temporary stairs work well because the transfer is right there. Before, riders had to travel these switchback ramps. Now they go to the end of the platform, and the transfer is easier. Its forecasting the simplicity of the future Transit Center. Once you have a direct orientation, the travel time gets reduced.

    What will be your favorite part of the new Transit Center when its done?

    When its done, that will be my favorite part! I've been working since 2002 on this job. Its been a challenge in terms of getting all the designs completed. Getting all the stakeholders informed. Making sure that logistically everything works properly, making sure the community is satisfied.

    Part of that challenge has been learning how to build complex projects in the urban environment. That is going to be something I learned from this project. Theres so much to think about on a complicated job like this: You have to deal with the level of the water table, with site logistics, with so many utilities, with underpinning of buildings, with local businesses, with people, transfersall the things that have gone into this project, I will take from it and learn.

    Working in a busy urban environment is a challenge -- yet its part of the total experience. It is very complex in its nature, and it brings so many things together in terms of its complexities. It is something Ill never forget.

  8. #848

    Default Corbin Building - Built in 1879....(4 Years before Brooklyn Bridge opened)

    Today....Awaiting restoration...
    Attached Thumbnails Attached Thumbnails Click image for larger version. 

Name:	DSC_0009.jpg 
Views:	238 
Size:	82.1 KB 
ID:	9358   Click image for larger version. 

Name:	DSC_0001.jpg 
Views:	193 
Size:	113.5 KB 
ID:	9357  

  9. #849
    NYC Aficionado from Oz Merry's Avatar
    Join Date
    Oct 2002
    Location
    Australia
    Posts
    7,478

    Default

    Fulton Transit Center on Track for 2014 Completion

    By Matt Dunning



    Authority has been hard to come by as of late, but one of the agency’s major capital projects is being viewed with optimism.

    Construction of the Fulton Street Transit Center, nicknamed the “Grand Central of Lower Manhattan,” has proceeded apace in the 12 months since the agency revised the $1.4 billion project’s schedule. MTA officials say the sprawling station remains on track to open in the summer of 2014.

    “The project is doing very well,” Uday Durg, the MTA’s program executive in Lower Manhattan, told a Community Board 1 committee last month. “All of our contracts are on or ahead of schedule.”

    Below is a brief progress report of projects within the transit center:

    THE NEXT TO OPEN
    While none of the projects connected to the transit station will open this year, several will be completed and open to the public in 2011. The southbound Cortlandt Street station—closed since Sept. 11, 2001—will open in time for the 10th anniversary of the attacks, Durg said. A new connector tunnel between the 4/5 and A/C lines and entrances to the 4/5 train at William Street also will open next year.

    STATION REHABILITATION
    Work on the Fulton Street station platforms has been ongoing since 2006. New entry stairways and elevators were installed along the 4/5 and 2/3 stations in 2007 to relieve congestion and platform crowding. The final contract for the 4/5 rehabilitation was awarded in August. That work is expected to be complete in 2012.

    CORBIN BUILDING RESTORATION
    Crews have spent close to a year carefully excavating the earth beneath the 112-year-old Corbin Building in order to prepare it for integration into the main Fulton Transit Center building. When it opens, in 2013, it will house ground floor retail spaces and serve as the south entrance to the new transit hall. Stabilizing the buildings, Durg said, “was one of the most challenging projects, at least in my 25 years working in New York.

    TRANSIT CENTER BUILDING
    Steel girders for the foundation of the new transit center’s glimmering main hall reached street level late last year, and the building’s circular mezzinine is beginning to take shape in the center of the framework. The underground steel work is expected to be completed in August. Due to open in June 2014, the hall will be one of the last of the projects to be completed.

    OTHER PROJECTS
    The Dey Street Concourse, connecting the R/W and 4/5 stations by way of an underground tunnel, is scheduled to open in 2012, as will new escalators to the 4/5 station at John Street and a new entrance at Dey Street and Broadway. The reworked A/C mezzanine, once a complex series of ramps between Nassau and William Streets, will reopen in 2013.

    http://www.tribecatrib.com/news/2010...ompletion.html

  10. #850
    Senior Member
    Join Date
    Oct 2002
    Location
    NYC - Hoboken
    Posts
    269

    Default

    Here are some pictures from yesterday. Looks like they are on schedule to complete the underground work for the station by August



  11. #851
    Moderator NYatKNIGHT's Avatar
    Join Date
    Oct 2002
    Location
    Manhattan - South Village
    Posts
    4,240

    Default

    Nice view - they're moving right along now. Looked to me like they started cleaning the Corbin Building too, along the John St. side.

  12. #852

    Default From this morning

    .
    Attached Thumbnails Attached Thumbnails Click image for larger version. 

Name:	DSC_0001.jpg 
Views:	921 
Size:	77.4 KB 
ID:	9899   Click image for larger version. 

Name:	DSC_0003.jpg 
Views:	129 
Size:	68.7 KB 
ID:	9898   Click image for larger version. 

Name:	DSC_0005.jpg 
Views:	884 
Size:	82.8 KB 
ID:	9900   Click image for larger version. 

Name:	DSC_0006.jpg 
Views:	136 
Size:	72.1 KB 
ID:	9901  

  13. #853

  14. #854

    Default

    That Payless shoe store and the white turd next to it need to go ASAP. It's a shame that the MTA did not seize those dumps for the station entrance on that side of B'Way.


  15. #855

    Default

    Hopefully they'll spruce them up when construction starts.

Similar Threads

  1. Winter Garden of World Financial Center - Recent pictures
    By Edward in forum New York City Guide For Visitors
    Replies: 166
    Last Post: August 31st, 2016, 01:04 PM
  2. Rockefeller Center Christmas Tree
    By Edward in forum New York City Guide For Visitors
    Replies: 16
    Last Post: December 21st, 2010, 10:17 PM
  3. Worthy Transit Improvements
    By Thomas in forum New York City Guide For New Yorkers
    Replies: 262
    Last Post: December 30th, 2008, 01:48 PM
  4. Transit Plan for Lower Manhattan
    By amigo32 in forum New York City Guide For New Yorkers
    Replies: 51
    Last Post: March 21st, 2008, 02:24 PM
  5. Jazz at Lincoln Center - Time Warner Center
    By Edward in forum New York Skyscrapers and Architecture
    Replies: 8
    Last Post: October 16th, 2007, 01:47 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  


Google+ - Facebook - Twitter - Meetup

Edward's photos on Flickr - Wired New York on Flickr - In Queens - In Red Hook - Bryant Park - SQL Backup Software