Thread: East Side Access - L.I.R.R. Link to Grand Central

  1. #136
    Senior Member
    Join Date
    Nov 2002
    Location
    Huntington
    Posts
    437

    Default

    Looks like another spate of articles on the project is out - they are still making nice progress:

    http://www.greenwichtime.com/local/a...ore-340914.php
    Crews have opened up a 65-foot-wide and 40-foot-high gouge to house a westbound platform space at the end of two 22-foot diameter tunnels, though work on the two lower level platforms will require excavating another 40 to 50 feet down
    ...
    When complete, there will be three new concourses running north to south from underneath the Roosevelt Hotel to Park Avenue, covering about 355,000 square feet, including about 91,000 square feet of public space for shops, ticket offices, pathways into Grand Central and other amenities.

    A total of 17 escalators will be built to carry passengers up and down from the four-platform terminal, work that requires excavation of four separate shafts about 100 feet deep
    Some nice photos here:
    http://gothamist.com/2010/01/29/mta_..._in_massiv.php

    And for the aurally attuned - an Audio Postcard from WNYC (a nice slideshow here too):
    http://www.wnyc.org/news/articles/149314

  2. #137

    Default

    July 24, 2011

    Deep Below Park Avenue, a Monster at Rest


    By MICHAEL M. GRYNBAUM

    Rome has the catacombs; Paris has its sewers. Now New York will have its own subterranean wonder: a 200-ton mechanical serpent’s head.

    It is a gargantuan drill that has been hollowing out tunnels for a train station under Grand Central Terminal. As tall as four men and with the weight of two whales, the so-called cutter head — the spinning, sharp-edged business end of a tunnel boring machine — is usually extracted, dismantled and sold for scrap when the work is done.

    But the Spanish contractor overseeing the project is taking a different approach. It believes it can save time and money by simply leaving it behind, dormant and decayed, within the rocky depths of Midtown Manhattan. The drill’s final resting place: 14 stories beneath the well-tended sidewalks of Park Avenue.

    There is little precedent for such a Brobdingnagian burial. No one at the Metropolitan Transportation Authority, which plans to officially entomb the machine sometime this week, can recall such an interment. “It’s like a Jules Verne story,” Michael Horodniceanu, the authority’s chief of construction, said.

    A recent visit to the cutter’s future crypt revealed a machine that evokes an alien life form that crashed to earth a millennia ago. Its steel gears, bolts and pistons, already oxidizing, appeared lifeless and fatigued. A wormlike fan, its exhaust pipe disappearing into the cutter’s maw, was still spinning, its drone not unlike a slumbering creature’s breath.

    “If you came and visited this 100 years from today, this is what you’d see,” said Dr. Horodniceanu, balancing on a catwalk that overlooks the enormous contraption. “People would not know what it’s all about.”

    The cutter head, known as Seli after its Italian manufacturer, has been eating its way through several miles of Manhattan schist since 2007. Its flat face is equipped with 45 rotating discs, each carrying a layer of tungsten carbide, an exceptionally strong alloy that can easily break through the city’s bedrock. (Rumors that the machine used diamonds for this purpose were “an urban legend,” according to a transportation authority spokesman.)

    Starting in 2016, the 22-foot-diameter tunnels created by the cutter will carry thousands of Long Islanders into a station beneath Grand Central Terminal. Today, the passages are craggy and unfinished, suggesting the ominous, organic look of a monster’s cave.

    Seli cost $6 million to $8 million, but Dragados, the project’s chief contractor and operator of the machine, decided this year that a scrap sale would not be economical. It can take months to dismantle a cutter, and the parts would have to be hauled from Midtown to the tunnel’s other end in Sunnyside, Queens. The removal would delay further construction, potentially costing millions of dollars in additional wages.

    “It costs, in effect, $100,000 a day just to be there — to say, ‘Hello!’ ” Dr. Horodniceanu said. “A machine like this, they want to spend $9 million pulling it out? You must be kidding me. It’s not happening.”

    Burial is more common for cutters in international tunneling projects. But the approach has rarely been tried in New York, whose crowded underground does not often have room.

    The new Second Avenue subway line ends at the 63rd Street F train station, not an ideal cemetery plot. On the No. 7 line, which is being extended to the Far West Side, the burial would have to take place beneath the Port Authority Bus Terminal, “and you can’t bury it in the Port Authority, very simply put,” Dr. Horodniceanu said.

    But the grassy Park Avenue median, between 37th and 38th Streets, did not pose a problem. And extracting the cutter from that location was out of the question. “There would had to have been a 40-foot-diameter shaft right in Park Avenue, in front of the Union League Club, to pull it out,” said Mark Rhodes, an engineer on the project.

    That image prompted Dr. Horodniceanu to laugh. “As it is, we don’t have many friends,” he said, shaking his head.

    A man who answered the phone at the Union League Club said the organization would not comment about the clubhouse’s new underground neighbor. But he conceded that the members were “painfully aware” of the construction occurring 140 feet beneath their gilded lobby.

    In an official ceremony this week, the cutter will be sealed off by a concrete wall; the chamber will then be filled with concrete, encasing the cutter in a solid cast, Han Solo-style, so that it can serve as a support structure for the tunnel. A plaque will commemorate the site. A spokesman said the pouring of the concrete was expected to take place on Wednesday.

    One might wonder what future generations will think if and when the cutter is ever dug up. In “Beneath the Planet of the Apes,” an astronaut discovers the ruins of the Queensboro Plaza subway station, colorful tiles still intact. (Queensboro Plaza is an elevated station, but the film does get credit for trying.) In that instance, the discovery prompted the horrifying revelation that Earth was destroyed in a nuclear holocaust and is now overrun by a race of intelligent apes.

    Dr. Horodniceanu did not quite envision that same situation for Seli.

    “People will find it, and they will find it exciting to see it, if they ever unearth it,” he said. “Who knows? Maybe they will want to continue the railroad south, at which point they would have to take it out.”

    Dr. Horodniceanu pondered that a moment: “Not an easy thing if they want to take it out.” He shrugged. “If they want to take it out, they will not look upon us favorably that we left it behind.”


    The 200-ton, 22.5-foot diameter tunnel-boring drill.


    An underground stretch that is being excavated for a train station under Grand Central Terminal. To save time and money, the Spanish contractor overseeing the project will leave the drill behind in Midtown, instead of extracting, dismantling and selling it for scrap.



    © 2011 The New York Times Company

  3. #138
    Forum Veteran macreator's Avatar
    Join Date
    Feb 2005
    Location
    East Midtown
    Posts
    1,398

    Default

    How great would it be if they kept digging southward to Penn to create a new shuttle between two major hubs? One can dream...

  4. #139
    Forum Veteran
    Join Date
    Oct 2009
    Location
    On the Rails in North NJ
    Posts
    2,585

    Default

    Quote Originally Posted by macreator View Post
    How great would it be if they kept digging southward to Penn to create a new shuttle between two major hubs? One can dream...
    Yea but then they have to enlarge all the current station and tunnel to hold Catenary for NJT and Amtrak and i doubt that would happen.

  5. #140
    Senior Member Bob's Avatar
    Join Date
    Jun 2004
    Location
    Fairfax, VA
    Posts
    926

    Default

    Could serve as a very unique tourist spot, for the right investor.

  6. #141

    Default

    Quote Originally Posted by Bob View Post
    Could serve as a very unique tourist spot, for the right investor.
    Thats actually not a bad idea.....

  7. #142
    Random Personality
    Join Date
    Aug 2005
    Location
    Woodside, Queens
    Posts
    950

    Default

    Recent video of one of the tunnel boring machines in Queens breaking through under the Sunnyside Yards. Not sure who at the MTA picks the music, but it is a strange selection IMHO:

    http://www.youtube.com/watch?v=jJsp6...feature=relmfu

  8. #143
    Random Personality
    Join Date
    Aug 2005
    Location
    Woodside, Queens
    Posts
    950

    Default

    Apparently the MTA's flickr account is frequently updated with pictures of the East Side Access Developments here.
    Last edited by ramvid01; February 23rd, 2012 at 12:11 AM. Reason: Couldn't embed some flickr pictures.

  9. #144
    Random Personality
    Join Date
    Aug 2005
    Location
    Woodside, Queens
    Posts
    950

    Default

    Another video update from the MTA on this project posted 2 days ago. Some interesting information on how they will dig under the elevated lines in LIC:

    http://www.youtube.com/watch?v=cdIq8...d5FAAAAAAAAAAA

  10. #145

    Default

    Shouldn't their be a station at Sunnyside?

  11. #146
    Forum Veteran
    Join Date
    Oct 2009
    Location
    On the Rails in North NJ
    Posts
    2,585

    Default

    It depends if theres any space left after the Amtrak Interchange is completed...

  12. #147
    Random Personality
    Join Date
    Aug 2005
    Location
    Woodside, Queens
    Posts
    950

    Default

    I don't recall hearing that it was canceled.I would not be surprised however that it was nixed.

  13. #148
    Forum Veteran
    Join Date
    Feb 2008
    Location
    New York City
    Posts
    2,129

    Default

    Skillman Ave and 39th street:





    Anybody knows what this is going to be - a new LIRR passenger station?

  14. #149
    Forum Veteran
    Join Date
    Oct 2009
    Location
    On the Rails in North NJ
    Posts
    2,585

    Default

    Emergency Exit and Access.....there are talks of a Sunnyside Station but that is a decade out.

  15. #150
    Forum Veteran
    Join Date
    Feb 2008
    Location
    New York City
    Posts
    2,129

    Default

    pretty elaborate for an emergency exit

Page 10 of 13 FirstFirst ... 678910111213 LastLast

Similar Threads

  1. The gantry of the float bridge of New York Central Railroad
    By Edward in forum New York City Guide For Visitors
    Replies: 19
    Last Post: March 21st, 2011, 04:16 PM
  2. Night owls released in Central Park
    By Edward in forum New York City Guide For New Yorkers
    Replies: 9
    Last Post: February 4th, 2011, 09:53 AM
  3. The float bridges of the New York Central Railroad
    By Edward in forum New York City Guide For Visitors
    Replies: 6
    Last Post: January 17th, 2004, 05:13 PM
  4. Central Synagogue - 652 Lexington Avenue
    By Edward in forum New York City Guide For Visitors
    Replies: 4
    Last Post: February 21st, 2003, 10:49 AM
  5. Central Park at dusk and Manhattan skyline
    By Edward in forum Photos and Videos of New York
    Replies: 1
    Last Post: February 11th, 2002, 05:37 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  